Centralia Schools Continue Planning of Science Wing Addition to High School

The Centralia School Board heard a presentation at its latest meeting from Paragon Architecture about an upcoming science wing addition to the high school. Superintendent Dr. Steven Chancellor outlines how the science wing will look.

The district plans to put the project out for bid in mid-November. Chancellor says construction will start shortly after the bidding process is complete.

The district is also planning renovations to the high school’s bathrooms and main office as well as the addition of an elementary school playground. The estimated cost of all of the projects is about 6.5 million dollars.